Background
Jai Raj Ispat Ltd. (JRIL) embarked on an ambitious ₹2000 crore expansion project to establish a 0.45 MTPA Integrated Steel Plant at Kurnool, Andhra Pradesh.
The integrated complex comprising Sinter Plant, Blast Furnace, Steel MeltingShop (SMS) and Rolling Mill was planned for simultaneous completion within 18 months, targeting mid-2021.
However, as execution progressed, momentum dropped sharply. After 2.5 months into execution, the portfolio was already delayed by 9 months. By mid-phase:
Recognizing the need for fundamental execution change, JRIL onboarded Realization Technologies to turn around the project and restore predictability.
Why Timely Delivery Was Critical?
For JRIL, this expansion was a strategic, high-stakesinvestment
Direct Financial Impact:
Given these stakes, timely delivery wasn’t just desirable it was existential for JRIL’s business continuity and growth.
Challenges Before the Intervention
1. Lack of Predictability
Over 2.5 years of execution, every six months brought 2–3months of additional delay, creating a recurring slippage cycle. There was no reliable forecast or baseline, making planning and decision-making difficult.
2. Continuous Cost Escalations
With scope additions, rework, and delayed deliveries, project costs were rising steadily, pushing the project beyond the approved capex & stressing financials and investor confidence.
3. Difficulty in Freezing Scope
Repeated design and engineering changes such as new BlowerHouse, SGP piping, and LCSS works led to continuous churn and lack of closure.
4. Limited Resources
Available manpower and supervision hovered at 50–60% of planacross all packages. This shortage reduced productivity and created execution bottlenecks everywhere.
Different teams (Civil, Mechanical, Structural andElectrical) were all trying to work in same spaces, causing clashes and slowdowns.
5. Failing Commitments from Contractors and Suppliers
Suppliers missed promised delivery timelines by 150–300%,while contractors struggled to maintain progress amid incomplete inputs. Deliveries were scattered and incomplete, leaving materials lying unused and tying upcash.
6. Weak Internal Capacity
The result was multiple fronts open, constant firefighting, and low delivery reliability. Managing so many moving parts was a huge challenge, especially with 100+ vendors & 30+ contractors operating without a common plan for delivery.
Earlier Approach to Project Delivery
Before Realization’s intervention, the JRIL team relied on conventional management methods:
While these practices worked for smaller projects, they proved inadequate in a large-scale, multi-front program with chronic shortages and shifting priorities.
New Approach – Realization Intervention
At the start of the engagement, JRIL and Realization jointly agreed on three core principles to help the existing team deliver more with the resources they already had:
Execution Solutions Implemented
1. Focus & Finish Execution
From the beginning, the JRIL project struggled with unfinished sections and overlapping activities. To fix this, the team introduced Focus & Finish execution rules. Execution zones were reorganized to reduce overlap and coordination clutter.
·The most coordination-heavy zones were identified early. Instead of spreading manpower across many half-done areas, eachwork area was defined for complete finish before moving to the next.
In structural erection, for instance, foundations, fabrication, and erection for each grid were completed end-to-end.
This drastically reduced rework and enabled steady progress despite manpower shortages
2. Resource Prioritization and Concentration
With only 50–60% manpower mobilized, resource concentrationbecame the central strategy.
3. Full Kitting for Procurement Synchronization
Procurement was restructured to match site readiness:
4. Streamliner for Control and Visibility
Realization’s digital platform Streamliner became the execution backbone.
Results Achieved
After 2.5 years of execution, the program which was already 9months behind with key fronts stalled. JRIL & Realization achieved one of the most remarkable turnarounds in its execution history:
For the remaining scope, Realization committed 14 months and delivered in 16 months. All four units of the 0.45 MTPA integrated steel complex were completed within this period:
· Rolling Mill: commissioned in 8th month
· Blast Furnace: completed in 11th month
· Steel Melting Shop (SMS): completed in 11th month
· Sinter Plant: completed in 16th month
All this was achieved with the same level of manpower(50–60%) and while still facing supplier delays; by simply improving focus,sequencing, and coordination.
The integrated plant was ultimately delivered within 1.5–2.5 months of feasible schedule, achieving predictable progress across all fronts.
Impact
Conclusion
The JRIL Integrated Steel Plant turnaround demonstrates that even in highly constrained environments with limited resources, delayed inputs,and complex interfaces. Execution speed and predictability can be achieved through disciplined focus, clear prioritization, and data-driven control.
By implementing the Focus & Finish methodology, resource concentration, and Streamliner-enabled visibility, JRIL delivered faster,steadier, and with far greater confidence, setting a new internal standard for how large capital projects should be managed.
“With the same resources and despite additional supplier delays, we delivered our Rolling Mill, Blast Furnace, and SMS within months, a feat that redefined how we manage large-scale execution at JRIL.”
https://www.youtube.com/watch?v=53FdjyPd88U&list=PLupBrPbgiU6PMNLMcpa86j3IEZP0WD7RV
1. Lack of Predictability
2. Continuous Cost Escalations
3. Difficulty in Freezing Scope
4. Limited Resources
5. Failing Commitments from Contractors and Suppliers
6. Weak Internal Capacity
1. Focus & Finish Execution
2. Resource Prioritization and Concentration
3. Full Kitting for Procurement Synchronization
4. Streamliner for Control and Visibility
1. Execution velocity improved from ~54% to near required speed
2. Predictability and control restored across 100+ contractors.
3. Enhanced reputation and stakeholder confidence due to disciplined delivery.
4. Established “Project Velocity” as a new benchmark metric for monitoring future expansions.
Share your contacts and we will set up a ‘Top-to-Top’ meet.