Almaraz Nuclear Power Plant – Major Shutdown Completed Ahead of Schedule

Case Summary

  • 01

    Challenges

    1. Not all tasks could be identified upfront
    2. Managing large temporary workforce
    3. Changing requirements
    4. Intense competition for resources
    5. Aligning internal and external stakeholders
  • 02

    Our Work

    1. 'Focus-&-Finish' approach
    2. Full kitting
    3. Business processes for proactive management
  • 03

    Results

    1. Shutdown 3 days early (65 days instead of 68 days)
    2. Power Uprating during the Shutdown: 6 days early (62 days instead of 68 days)

At Spain’s Almaraz Nuclear Power Plant, a major power-uprating programme required extensive engineering modifications and equipment upgrades to be completed within tightly planned shutdown windows. Using Realization’s Critical Chain Project Management (CCPM) software and a Focus & Finish execution approach, the plant completed its shutdown and power-uprating activities ahead of schedule.

The project: Increasing capacity while keeping shutdown time under control

Almaraz Nuclear Power Plant, located in Cáceres, Spain, operates two nuclear generating units. Its power-uprating programme was designed to increase generating capacity while modernising important plant systems and equipment. This was much more than a normal maintenance shutdown. It involved design modifications, equipment replacement, installation, integration and testing across several engineering disciplines.

The work included new alternators, changes to high-pressure turbines, pumps and cooling systems, and modifications to electrical and control equipment. The upgrades also involved more than 1,000 wired and communicated signals that had to be connected and checked. Much of the engineering, preparation and assembly could proceed while the plant was operating, but major installation and tie-in activities had to be completed during scheduled refuelling shutdowns.

The scale of the work was considerable. During the major power-uprating shutdown, the workforce grew to approximately 3,000 people from multiple specialist teams. Many were temporary resources, and not all were under the direct control of the plant’s project leadership. With the production value of a day of operation estimated at €1 million, every additional shutdown day mattered.

The challenge: Engineering delays before shutdown, resource conflicts during execution

The execution challenge had begun well before the shutdown itself. Almaraz was continuously carrying out engineering modifications to improve plant safety, reliability and operating efficiency. Individual design modifications could take one to six months, involving approximately 150 engineers across mechanical, electrical and other disciplines.

Although many projects were started, they did not always move steadily towards completion. Engineers could be waiting for decisions, inputs or approvals needed to progress. Meanwhile, other jobs would be released, increasing the number of activities competing for the same engineering capacity. Incomplete engineering work was a particular concern because design readiness determined what could be prepared and executed during the shutdown.

The outage introduced additional uncertainty. Some work could only be fully defined after inspections, when equipment conditions became known. New maintenance requirements could be identified after the shutdown had begun. At the same time, mechanical, electrical and instrumentation specialists, planners, supervisors, cranes and scaffolding had to be shared across numerous jobs. Delays or changes in one work area could disrupt the sequence of work in another.

The equipment modifications show why preparation and sequencing were so important. One of the major uprating activities involved replacing a generator stator weighing approximately 455 tonnes. At Unit 2, the existing turbine-hall crane was rated for 180 tonnes, so a temporary lifting arrangement had to be engineered and installed. That was one complex activity among many which had to fit into the shutdown programme alongside other modifications and testing.

The central issue was therefore not simply how to produce a detailed shutdown schedule. It was how to ensure that engineering work was completed in time, critical work fronts were ready to start, scarce specialist resources were not pulled in competing directions, and the many activities converged on the required completion date.

Realization’s approach: Focus & Finish, supported by CCPM software

Working with Realization’s Spanish partner, CMG Consultores, the Almaraz team adopted Realization’s Critical Chain Project Management (CCPM) software and a Focus & Finish execution approach. The approach changed how projects and shutdown activities were prioritised, prepared and released for execution.

Instead of starting as many activities as possible and then managing the resulting conflicts, the team followed a Focus & Finish approach. Larger management units were staggered, and the number of open execution tasks was controlled. This helped concentrate available resources on finishing important work rather than repeatedly moving between partly completed jobs.

Before a management unit was released, it went through a full-kitting process. Required information, decisions and other prerequisites were checked so that teams were less likely to start work and then stop for something that should have been prepared in advance.

Realization’s CCPM software provided a two-level planning and execution structure. At the planning level, management units were sequenced using Critical Chain principles, considering resource constraints and shared time buffers. At the execution level, detailed subtasks and checklists remained flexible so that teams could respond to actual site conditions and work discovered during inspections.

This distinction mattered. Leadership needed a stable view of the shutdown’s priorities and completion risks, while execution teams needed clear daily instructions that reflected changing conditions. The daily management process used Realization’s CCPM software to identify which tasks should proceed, where resources were required and what problems had to be resolved to protect the overall plan.

The approach was first applied to engineering activities. Following an initial pilot and implementation, the Almaraz–Trillo engineering team reported an improvement of more than 20% in process efficiency. The experience provided a basis for extending Realization’s CCPM software and execution practices to the much larger power-uprating programme.

The results: Shutdown and power uprating completed ahead of plan

The planned shutdown window was 68 days. The overall shutdown was completed in 65 days, three days ahead of plan. The power-uprating activities within the shutdown were completed in 62 days, six days ahead of the corresponding 68-day plan.

These were two milestones within the shutdown programme. The earlier improvement of more than 20% in engineering-process efficiency was a separate result from the preceding engineering implementation.

For Almaraz, the achievement was significant not merely because the shutdown finished early, but because it did so while accommodating major equipment replacements, modifications to plant systems, a large temporary workforce and changes that had to be verified before the plant returned to operation.

Javier Sáenz de Santa María, Head of Corporate Planning at Almaraz and Trillo Nuclear Power Plants, later acknowledged the contribution of the Critical Chain methodology and CMG–Realization support in enabling project activities to finish faster than scheduled.

What changed in the way the work was managed

The Almaraz experience demonstrated the value of addressing the flow of work before it becomes a shutdown problem. Engineering activities were managed towards completion rather than left open across too many simultaneous jobs. Work was prepared before release. Shared specialists and equipment were managed against common priorities. And the overall plan was protected without assuming that every execution-level activity could be defined perfectly in advance.

Realization’s CCPM software made these operating rules practical through Critical Chain planning, controlled work release, full-kitting, shared priorities and daily execution management. The result was a more reliable way to manage a complex programme in which engineering, installation and shutdown execution all had to come together within a demanding completion window.

‍

Read relevant articles:

Critical chain project management (CCPM): why projects remain late and how CCPM actually fixes it?

Why projects are late even when everything seems managed?

Beyond fragmentation: Toyota's cell manufacturing model offers a blueprint for construction

What if our best attempts to minimize time and cost overruns in projects are pointless?

How can we solve the late project problem

Implementing critical chain in large infrastructure projects

Part 1: Why critical chain is not a science

Part 2: Who said critical chain is not a science?

Part 3: Let's make critical chain a science

Contact us to find out more